On 17 December 2009 Gas Industry Co received a request from Maui Development Limited (MDL) to consider and make a recommendation in respect of proposed changes to the Maui Pipeline Operating Code (MPOC).
Working Paper - Comparison of 17 December 2009 MDL change request and draft balancing rules.
MDL has made a number of minor and technical changes to the December Change Request following an industry workshop to discuss the change.
MPOC Change Request (Revised version)
MPOC Change Request Marked Up (Revised version)
Following feedback on the Status Update, Gas Industry Co has revised its original timetable for making a draft recommendation, obtaining submissions on that draft, and making its final recommendation to MDL on the December Change Request.
|
Date |
Step |
|
21 December 2009 |
Gas Industry Co calls for submissions on change request |
|
5 February 2010 |
Close of submissions on change request |
|
7 May 2010 (was 5 March) |
Gas Industry Co releases draft recommendation and calls for submissions |
|
4 June 2010 (was 2 April) |
Close of submissions on draft recommendation |
|
2 July 2010 (was 23 April) |
Gas Industry Co makes recommendation to MDL |
Gas Industry Co has prepared a Status Update on the December Change Request.
Having considered submissions made in respect of this change request, Gas Industry Co has prepared the following draft recommendation.
Gas Industry Co has considered submissions on the draft recommendation and has prepared a draft final recommendation. Because the final recommendation differs from the draft, we invite submissions on this draft Final Recommendation.
We will consider whether any issues raised in submissions cause us to reconsider our draft Final Recommendation. If submissions do not change this determination, we will finalise the recommendation and submit it to MDL. Alternatively if, after considering submissions we wish to alter our draft final recommendation, we will revise the draft and consult on it one last time before finalising.